Current Projects
[ Current Projects | Completed Projects | Future Projects ]
View Progress Chart | View Capital Projects Map |
Details of Current Capital Projects
Each capital project requires approval from the Ministry of Infrastructure. A status update of each is provided below. This page is updated monthly, following each Board Meeting. Please note: as projects proceed and circumstances become better clarified, the dates below are subject to change.

Kwantlen Park Secondary Addition (Site 048)
- Address: 10441 132 St, Surrey, BC V3T 3V3
- Project Type: Addition, 20 classrooms
- Approval: Ministry of Education and Child Care approval January 10, 2023
- Current Phase: Construction 35%
- Construction Contract: Olivit Construction Ltd.
- Target Occupancy: September 2027
Guildford Park Secondary Addition (Site 047)
- Address: 10707 146 St, Surrey, BC V3R 1T5
- Project Type: Addition, 14 classrooms
- Approval: Ministry of Education and Child Care approval May 26, 2023
- Current Phase: Construction 23%
- Construction Management Services: Unitech Construction Management Ltd.
- Target Occupancy: June 2028
Tamanawis Secondary Addition (Site 150)
- Address: 12600 66 Ave, Surrey, BC V3W 2A8
- Project Type: Addition, 23 classrooms
- Approval: Ministry of Education and Child Care approval May 9, 2023
- Current Phase: Construction 38%
- Construction Contract: D.G.S. Construction Company Ltd.
- Target Occupancy: September 2027
Old Yale Road Elementary Prefab Addition (Site 064)
- Address: 10135 132 St, Surrey, BC V3T 3T6
- Project Type: Pre-fabricated Modular Addition, 10 classrooms + 7 More (17 total)
- Approval: Ministry of Education and Child Care approval May 16, 2024 for 10 classrooms; July 5, 2024 for additional 7 classrooms
- Current Phase: Construction 60%
- Construction Management Services: Heatherbrae Builders Co. Ltd.
- Target Occupancy: January 2027
Martha Currie Elementary Prefab Addition (Site 061)
- Address: 5811 184 St, Surrey, BC V3S 4N2
- Project: Pre-fabricated Modular Addition, 6 classrooms
- Approval: Ministry of Education and Child Care approval May 16, 2024
- Current Phase: Construction 47%
- Construction Management Services: Unitech Construction Management Ltd.
- Target Occupancy: October 2026
Latimer Road Elementary Prefab Addition (Site 035)
- Address: 19233 60 Ave, Surrey, BC V3S 2T5
- Project Type: Prefabricated Modular Addition, 6 classrooms
- Approval: Ministry of Education and Child Care approval July 5, 2024
- Current Phase: Construction 75%
- Construction Management Services: Heatherbrae Builders Co. Ltd.
- Target Occupancy: September 2026
William Watson Elementary Prefab Addition (Site 057)
- Address: 16450 80 Ave, Surrey, BC V4N 0H3
- Project Type: Prefabricated Modular Addition, 12 classrooms
- Approval: Ministry of Education and Child Care approval July 5, 2024
- Current Phase: Construction 27%
- Construction Management Services: Unitech Construction Management Ltd.
- Target Occupancy: November 2026
George Greenaway Elementary Prefab Addition (Site 090)
- Address: 17285 61a Ave, Surrey, BC V3S 1W3
- Project Type: Addition, 14 classrooms
- Approval: Ministry of Education and Child Care approval September 9, 2024
- Current Phase: Construction 43%
- Construction Management Services: Unitech Construction Management Ltd.
- Target Occupancy: January 2027
Forsyth Road Elementary Addition (Site 183)
- Address: 10730 139 St, Surrey, BC V3T 4L9
- Project Type: Addition, 14 classrooms
- Approval: Ministry of Education and Child Care approval June 10, 2024
- Current Phase: Construction 0%
- Construction Management Services: Pro-Can Construction Group Corp.
- Target Occupancy: Fall 2028
Fleetwood Park Secondary Addition (Site 167)
- Address: 7940 156 St, Surrey, BC V3S 3R3
- Project Type: Addition, 32 classrooms
- Approval: Ministry of Education and Child Care approval June 27, 2024
- Current Phase: Design
- Tender: Fall 2026
- Target Occupancy: Spring 2029
Clayton Heights Secondary Addition (Site 175)
- Address: 7003 188 St, Surrey, BC V4N 3G6
- Project Type: Addition, 41 classrooms
- Approval: Ministry of Infrastructure approval July 4, 2025
- Current Phase: Design
- Tender: Summer 2027
- Target Occupancy: Fall 2029
Grandview Heights Secondary Addition (Site 177)
- Address: 16987 25 Ave, Surrey, BC V3Z 0Z9
- Project Type: Addition, 20 classrooms
- Approval: Ministry of Infrastructure approval February 10, 2026
- Current Phase: Design
- Tender: Spring 2027
- Target Occupancy: Fall 2029
Redwood Park New Elementary School (Site 214)
- Address: 17320 and 17390 20 Avenue area
- Project Type: New School, 37 classrooms
- Approval: Awaiting funding from Ministry of Infrastructure
- Current Phase: Planning, Business Case
- Tender: Pending Ministry of Infrastructure funding approval
- Target Occupancy: Pending Ministry of Infrastructure funding approval