School Construction Progress

[ Progress Chart | Project Details | Future ProjectsCompleted Projects ]
[ 2022-23 Five Year Capital Plan | Capital Plan Summary: English / Mandarin / Punjabi ]

Approved Projects

A project is considered approved once funding has been committed from the Ministry of Education. Normally, there is an initial announcement by the Ministry of Education which is support to proceed to prepare a Project Definition Report (PDR). Any project on this list has received funding required for design and construction.

This Progress Chart is updated following each board meeting.


Logo
Date of Approval
Design Complete
Tender Award
Construction Completion
Open for Students

#218 Regent Road Elementary

New School
27 Classrooms

Aug. 9, 2017

Completed
Awarded

71%

Sep 2022

#164 Sullivan Heights Secondary

Addition
28 Classrooms

Jul. 10, 2018

Completed
Awarded

74%

Sep 2022

Seismic Upgrade
Aug. 27, 2019
Completed
Awarded
76%
Apr 2022
Seismic Upgrade
Aug. 27, 2019
Completed
Awarded
85%
Apr 2022

#009 White Rock Elementary

Addition
8 Classrooms

Apr. 20, 2020

Completed
Awarded

30%

Oct 2022

#202 Sunnyside Elementary

Addition
10 Classrooms

Feb. 11, 2020

Completed
Awarded

44%

Oct 2022

#188 Morgan Elementary

Addition
8 Classrooms

Jun. 3, 2020

Completed
Awarded
20%

May 2023

Seismic Upgrade
Apr. 23, 2019
Completed
Awarded
89%
Sep 2022
Seismic Upgrade
Jul. 15, 2020
Completed
Awarded
91%
Sep 2022

#207 Ta'talu Elementary School

New School
27 Classrooms

Apr. 6, 2020

Winter 2021

Apr 2022


Fall 2024

#040 K.B. Woodward Elementary

Addition
8 Classrooms

Jun. 8, 2020

Completed
Awarded

34%

May 2023

#115 Snokomish Elementary

New School
27 Classrooms

Apr. 28, 2021

Spring 2023

Spring 2023


Spring 2025

#118 South Meridian Elementary

Addition
8 Classrooms

Aug. 12, 2021

Spring 2023
Spring 2023

Fall 2024

#161 Semiahmoo Trail Elementary

Addition
10 Classrooms

Aug. 12, 2021

Spring 2023
Spring 2023

Fall 2024

Supported Projects (Pending Ministry of Education Funding approval)
#048 Kwantlen Park Secondary
10441 132nd St.
Addition
12 Classrooms

Pending



#047 Guilford Park Secondary
10707 146th St.
Addition
18 Classrooms

Pending




#150 Tamanawis Secondary
12600 66th Ave. 
Addition
23 Classrooms

Pending




#167 Fleetwood Park Secondary
7940 156th St.
Addition
23 Classrooms

Pending




Design

Following approval of the funding agreement with the Ministry of Education, the Design stage begins.
Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a detailed design. This detailed design is used to secure City of Surrey development/building permits and are part of the tender package.

Tender

When a project's design is complete, the project is put to tender. Construction companies bid on the contract to build new schools and expansions.

Construction

After the project has been awarded to the successful bidder, construction can begin.
This stage has many varying factors that can affect the length of time required to finish a project.

Target Occupancy

At the Target Occupancy stage, we furnish, fit and occupy the new development. While the building is now being used as planned, minor work continues.