Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education and Child Care funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

  • The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
  • This progress chart is updated following each board meeting.

Logo
Approval
Design
Tender
Award
Construction
Completion*
Projected Occupancy
Open for
Students

#207 Ta'talu Elementary

27-Classroom
New School
Apr 6, 2020
Design Complete
Awarded
88%
Jan 2025

#118 South Meridian Elementary

8-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
32%
May 2025

#161 Semiahmoo Trail Elementary

10-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
31%
May 2025

#115 Snokomish Elementary

27-Classroom
New School
March 30, 2021
Design Complete
Awarded
7%
March 2026
20-Classroom
Addition
Jan 10, 2023
In process
Spring 2025
0%
Fall 2027
#047 Guildford Park Secondary
18-Classroom
Addition
May 26, 2023
In process
Fall 2025
0%
Spring 2028
23-Classroom
Addition
May 9, 2023
In process
Fall 2025
0%
Spring 2028
#055 Lena Shaw Elementary8-Classroom Modular AdditionSep 27, 2023In ProcessSpring 20240%Fall 2024
12-Classroom Modular Addition
Sep 27, 2023
In Process
Spring 2024
0%
Fall 2024
#145 Woodland Park Elementary16-Classroom Modular AdditionSep 27, 2023In ProcessSpring 20240%Fall 2024

BUILDING ENVELOPE PROJECTS





#022 Queen Elizabeth
Secondary
BEP
Approved
In process


Pending
#150 Tamanawis
Secondary
BEP
Approved
In process


Pending







SUPPORTED PROJECTS (Pending Ministry of Education Funding Approval)
20-Classroom
Addition
Pending




20-Classroom
Addition
Pending




8-Classroom
Addition 
Pending




*This column represents the percentage of the contract value that has been paid out to the contractor.

Design Stage
Following approval of the funding agreement with the Ministry of Education, the design stage begins. Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage
When a project's design is complete, it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage
After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors that affect the amount of time required to finish a project.

Occupancy Stage
In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.