Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education and Child Care funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

  • The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
  • This progress chart is updated following each board meeting.

 


Logo





SiteDescription
Approval
Design
Tender
Award
Construction
Completion*
Projected Student Occupancy

207 Ta'talu Elementary

27-Classroom
New School
Apr 6, 2020
Design Complete
Awarded
90%
Jan 2025

118 South Meridian Elementary

8-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
50%
May 2025

161 Semiahmoo Trail Elementary

10-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
40%
May 2025

115 Snokomish Elementary

27-Classroom
New School
Mar 30, 2021
Design Complete
Awarded
19%
March 2026
145 Woodland Park Elementary
16-Classroom 
Modular Addition
Sep 27, 2023
Design Complete
Spring 2024
In process
Fall 2024

12-Classroom
Modular Addition

Sep 27, 2023
Design Complete
Spring 2024
In process
Fall 2024
055 Lena Shaw Elementary8-Classroom
Modular Addition
Sep 27, 2023
Design Complete
Spring 2024
In process
Fall 2024

20-Classroom
Addition

Jan 10, 2023
In process
Spring 2025
0%
Fall 2027
047 Guildford Park Secondary18-Classroom
Addition
May 26, 2023
In process
Fall 2025
0%
Spring 2028

23-Classroom
Addition

May 9, 2023
In process
Fall 2025
0%
Spring 2028

BUILDING ENVELOPE PROJECTS


#022 Queen Elizabeth Secondary

BEP
Approved
In process


Pending

#150 Tamanawis Secondary

BEP
Approved
In process


Pending

SUPPORTED PROJECTS - Pending Ministry Funding Approval


20-Classroom
Addition
Pending





20-Classroom
Addition
Pending





8-Classroom
Addition
Pending





37-Classroom
New School
Pending





20-Classroom
Addition
Pending











*This column represents the percentage of the contract value that has been paid out to the contractor.

Design Stage
Following approval of the funding agreement with the Ministry of Education, the design stage begins. Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage
When a project's design is complete it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage
After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors that affect the amount of time required to finish a project.

Occupancy Stage
In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.