Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

Once the Ministry of Infrastructure funding is committed, a new capital project is considered approved.

Normally, a public announcement is made when the Ministry gives its support to move forward on a project. The School District Capital Project Office then prepares and submits a Project Definition Report (PDR). Once the Ministry approves the PDR, the project receives funding and can proceed into design and construction.

  • The completion and occupancy dates in this report are target dates only and subject to change as projects proceed.
  • This progress chart is updated following each board meeting.
  • It is best to view this website from a desktop or laptop. You can scroll across to view full information.

 


Logo


Dated June 11, 2026
SiteDescription
Approval
Design
Tender
Award
Construction
Completion*

Projected Student Occupancy

20-Classroom
Addition

Jan 10, 2023
Design Complete
Awarded
35%
Sep 2027
14-Classroom
Addition
May 26, 2023
Design Complete
Awarded
23%June 2028
23-Classroom
Addition
May 9, 2023
Design Complete
Awarded
38%
Sep 2027
32-Classroom
Addition
June 27, 2024
In processFall 20260%Spring 2029

14-Classroom
Addition

June 10, 2024
Design Complete
Awarded0%Fall 2028
10 + 7 Classrooms
Prefabricated Addition
May 16 + July 5, 2024
Design Complete
Awarded60%Jan 2027
6-Classroom
Prefabricated Addition
May 16, 2024
Design Complete
Awarded47%Oct 2026

6-Classroom
Prefabricated Addition

July 5, 2024
Design Complete
Awarded75%Sep 2026
12-Classroom
Prefabricated Addition
July 5, 2024
Design Complete
Awarded27%Nov 2026

14-Classroom
Prefabricated Addition
Sep 9, 2024
Design Complete
Awarded43%Jan 2027
41-Classroom
Addition
July 4, 2025In processSummer 20270%Fall 2029
20-Classroom
Addition
Feb 10, 2026In processSpring 20270%Fall 2029
37-Classroom
New School

Pending
Planning


BUILDING ENVELOPE PROJECTS

022 Queen Elizabeth Sec
BEP
June 4, 2021
Design Complete
Awarded
2%
Spring 2027
150 Tamanawis Sec
BEP
June 4, 2021
In process



174 Kirkbride ElemBEPMarch 15, 2024Planning


162 Bayridge ElemBEPMarch 15, 2024
In process



028 North Surrey SecBEPMarch 15, 2024Planning


131 Hyland ElemBEPMarch 15, 2024
In process



158 Beaver Creek ElemBEPMarch 25, 2025Planning


140 Martha Jane Norris ElemBEPMarch 25, 2025Planning


041 Lord Tweedsmuir SecBEPMarch 25, 2025Planning


149 Sunrise Ridge ElemBEPMarch 25, 2025Planning


077 Royal Heights ElemBEPMarch 25, 2025Planning


*This column represents the percentage of contract value paid out to the contractor

Design Stage

Following approval of the funding agreement with the Ministry of Infrastructure, the design stage begins. Sketch plans / schematic designs are the preliminary design concept. The sketch plan then advances to a more detailed design, used to secure City of Surrey development / building permits. These designs are included in the bid tender package.

Tender Stage

When a project's design is complete it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage

After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors affecting the time required to finish a project.

Occupancy Stage

In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.