Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

  • The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
  • This progress chart is updated following each board meeting.

Logo
Date of
Approval
Design
Complete
Tender
Award
Construction
Completion*
Occupancy
Open for
Students

#040 K. B. Woodward Elementary

Addition
8 Classrooms

Jun. 8, 2020

Completed
Awarded

100%

Sep 2023

#207 Ta'talu Elementary

New School
27 Classrooms

Apr. 6, 2020

Completed
Awarded
39%Jan 2025

#118 South Meridian Elementary

Addition
8 Classrooms
Aug. 12, 2021Completed
Spring 2023

0%

Fall 2024

#161 Semiahmoo Trail Elementary

Addition
10 Classrooms
Aug. 12, 2021
In process
Spring 2023
0%
Fall 2024

#115 Snokomish Elementary

New School
27 Classrooms

March 30, 2021

In process

Spring 2023

0%

Spring 2026

#048 Kwantlen Park Secondary
Addition
11 Classrooms
Feb 22, 2023In processSpring 20250%Fall 2027
#150 Tamanawis Secondary
Addition
23 Classrooms
May 10, 2023In processFall 20250%
Spring 2028
#047 Guilford Park Secondary
Addition
18 Classrooms
May 26, 2023In processFall 2025
0%
Fall 2028

BUILDING ENVELOPE PROJECTS





#157 Coyote Creek
Elementary
BEP
CompletedAwarded40%Dec 2023
#022 Queen Elizabeth
Secondary
BEP
In process


#150 Tamanawis
Secondary
BEP
In process









SUPPORTED PROJECTS (Pending Ministry of Education Funding Approval)
#167 Fleetwood Park Secondary
Addition
20 Classrooms

pending



#175 Clayton Heights
Secondary
Addition
20 Classrooms
Pending



#183 Forsyth Road
Elementary
Addition
8 Classrooms
Pending










*This column represents the percentage of the contract value that has been paid out to the contractor.

Design Stage

Following approval of the funding agreement with the Ministry of Education, the design stage begins.
Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage

When a project's design is complete, it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage

After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors that affect the amount of time required to finish a project.

Occupancy Stage

In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.