Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

Once the Ministry of Education and Child Care funding is committed, a new capital project is considered approved.

Normally, a public announcement is made when the Ministry gives its support to move forward on a project. The school district's capital project office then prepares and submits a Project Definition Report (PDR). Once the Ministry approves the PDR, the project receives funding and can proceed into design and construction.

  • The completion and occupancy dates in this report are target dates only and subject to change as projects proceed.
  • This progress chart is updated following each board meeting.
  • It is best to view this website from a desktop or laptop. Otherwise, you can use the scroll bar at the bottom of the pages.

 


Logo


SiteDescription
Approval
Design
Tender
Award
Construction
Completion*
Projected Student Occupancy

118 South Meridian Elem

8-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
Construction Complete
May 2025

161 Semiahmoo Trail Elem

10-Classroom
Addition
Aug 12, 2021
Design Complete
Awarded
Construction Complete
June 2025

115 Snokomish Elem

27-Classroom
New School
Mar 30, 2021
Design Complete
Awarded
94%
Jan 2026
16-Classroom 
Prefabricated Addition
Sep 27, 2023
Design Complete
Awarded
90%
Sep 2025

12-Classroom
Prefabricated Addition

Sep 27, 2023
Design Complete
Awarded
100%
April 2025
152 Walnut Road Elem
4-Classroom (additional)
Prefabricated Addition
June 20, 2024Design CompleteAwarded75%Fall 2025

20-Classroom
Addition

Jan 10, 2023
Design Complete
Awarded
9%
Spring 2028
18-Classroom
Addition
May 26, 2023
Design Complete
Awarded
2%Spring 2028
23-Classroom
Addition
May 9, 2023
Design Complete
Summer 2025
1%
Spring 2028

167 Fleetwood Park Sec

32-Classroom
Addition
June 27, 2024
In processFall 20260%Jan 2029

14-Classroom
Addition

June 10, 2024
In process
Spring 20260%Fall 2028
064 Old Yale Road Elem
10 + 7 Classrooms
Prefabricated Addition
May + July '24
Design Complete
June 20251%Spring 2027







6-Classroom
Prefabricated Addition
May 16, 2024
Design Complete
June 20251%Fall 2026

6-Classroom
Prefabricated Addition

July 5, 2024
Design Complete
June 20251%Fall 2026
12-Classroom
Prefabricated Addition
July 5, 2024
Design Complete
June 20251%Spring 2027

14-Classroom
Prefabricated Addition

Sep 9, 2024
Design Complete
June 20251%Fall 2026

20-Classroom
Addition

July 4, 2025In processtbd0%tbd







BUILDING ENVELOPE PROJECTS

022 Queen Elizabeth Sec
BEP
June 4, 2021
In process



150 Tamanawis Sec
BEP
June 4, 2021
In process



174 Kirkbride ElemBEPMarch 15, 2024Planning


162 Bayridge ElemBEPMarch 15, 2024Planning


028 North Surrey SecBEPMarch 15, 2024Planning


131 Hyland ElemBEPMarch 15, 2024Planning


158 Beaver Creek ElemBEPMarch 25, 2025Planning


140 Martha Jane Norris ElemBEPMarch 25, 2025Planning


041 Lord Tweedsmuir SecBEPMarch 25, 2025Planning


149 Sunrise Ridge ElemBEPMarch 25, 2025Planning


077 Royal Heights ElemBEPMarch 25, 2025Planning










SUPPORTED PROJECTS - Pending Ministry Funding Approval








37-Classroom
New School
Pending
Planning




20-Classroom
Addition
Pending
Planning



*This column represents the percentage of contract value paid out to the contractor.

Design Stage

Following approval of the funding agreement with the Ministry of Education, the design stage begins. Sketch plans/schematic designs are the preliminary design concept. The sketch plan then advances to a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage

When a project's design is complete it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage

After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors affecting the time required to finish a project.

Occupancy Stage

In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.